With
respect to the liability of a promoter regarding the possession period in BBA
of pre-RERA time and completion period of an ongoing project as mentioned in
HRERA Registration Certificate, The Haryana Real Estate Appellate Tribunal in Appeal
No.21 of 2019 titled as M/s Pivotal Infrastructure Pvt. Ltd., Versus Prakash Chand Arohi, Decided on 20.05.2020 has categorically ruled at Para 73:
“We have duly considered the aforesaid
contentions. Likely or actual date of
completion of the project has been mentioned to be February, 2019 in the
Certificate of Registration granted by the learned Authority. This date might have been mentioned in the
Registration Certificate on the basis of declaration submitted by the promoter
under Section 4(2)(l)(C) of the Act at the time of getting the project
registered. This declaration is given
unilaterally by the promoter to the Authority at the time of getting the real
estate project registered. The allottee
had no opportunity to raise any objection at that stage, so this unilateral Act
of mentioning the date of completion of project by the builder will not
abrogate the rights of the allottee under the agreements for sale entered into
between the parties. The Division
Bench of the Hon’ble Bombay High Court in case Neel Kamal Realtors Suburban Pvt. Ltd. & anr. Vs. Union of India
and others (Supra) has laid down as under: -
“Section 4(2)(l)(C) enables the
promoter to revise the date of completion of project and hand over possession. The provisions of RERA, however, do not
rewrite the clause of completion or handing over possession in agreement for
sale. Section 4(2)(l)(C) enables the promoter to give fresh time line
independent of the time period stipulated in the agreements for sale entered
into between him and the allottees so that he is not visited with penal
consequences laid down under RERA. In
other words, by giving opportunity to the promoter to prescribe fresh time line
under Section 4(2)(l)(C) he is not absolved of the liability under the
agreement for sale.”
The Hon’ble Bombay High Court by taking
note of the provisions of section 4(2)(l)(c) of the Act has categorically laid
down that the provisions of the Act will not re-write the clause of completion
or handing over of the possession mentioned in the agreement for sale. The fresh time line independent of the time
stipulated in the agreement is given in order to save the developer from the
penal consequences but he is not absolved of the liability under the agreement
for sale. Thus, the appellant/builder was required to offer the possession of
the unit to the respondent/allottee as per the terms and conditions of the
agreements, failing which the respondent/allottee will be entitled to claim the
remedies as provided under section 18 of the Act.
http://mintuinfo.blogspot.com/2020/11/supreme-courtongoing-projecteffect-of.html
No comments:
Post a Comment